Alert #47 - September 21, 2012

The Riverside County Transportation Commission expects the new lanes on Interstate 215 between Murrieta Hot Springs Road and Scott Road to open Saturday morning, September 22.  However, temporary lane closures will continue for miscellaneous finishing work.  Previous restrictions on the outside shoulder width will be removed.

The 55 MPH speed limit will remain in place for a short time, since construction work is ongoing.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, September 24 through Thursday, September 27
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, September 28
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, September 24 through Thursday, September 27
Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, September 28
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect until Further Notice
The speed limit has been reduced to 55 mph and will remain in effect until further notice.  Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

Coming Soon…

Construction is scheduled to start in early 2013 on the I-215 Central Project, which will add a third lane to I-215 from Scott Road in Menifee to Nuevo Road in Perris. Once completed, the project will create three continuous northbound lanes and three continuous southbound lanes from I-15 to the 60/91 Interchange.

Please Join Us!

RCTC, Caltrans and project partners will mark the completion of the I-215 South Project and the beginning of the I-215 Central Project with a “Giving Thanks” ceremony on Monday, October 29 at the Shops at Scott in Menifee.

Please watch for more details.


WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #46 - September 13, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Temporary lane closures will be required to allow construction crews to continue with striping the new lanes, installation of roadway signs and ramp metering detectors.

Please be aware that outside freeway shoulders have been reduced in width to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, September 17 through Thursday, September 20
Lane closures will be required each night from 9 pm to 5 am the following morning. No detours will be required during these closures since at least one lane will remain open. 

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, September 17 through Thursday, September 20
Lane closures will be required each night from 10 pm to 6 am the following morning. No detours will be required during these closures since at least one lane will remain open. 

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound
I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:


Alert #45 - September 6, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction activity will require continued temporary lane closures to allow crews to install roadway signs and ramp metering detectors and stripe the freeway lanes.

Please be aware that outside freeway shoulders have been reduced in width to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, September 10 through Thursday, September 13
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, September 14
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open. 

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, September 10 through Thursday, September 13
Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, September 14
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound
I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:


  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info


Alert #44 - August 31, 2012

Date:  August 31, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

As described below, temporary nighttime freeway lane closures will continue to allow crews to install signs, stripe new lanes and install ramp metering loop detectors.

Please be aware that outside freeway shoulders have been reduced in width to eight feet within the project limits and will be in place for the duration of the project.

In observance of the Labor Day holiday, no closures will occur the evening of August 31 through September 3.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Tuesday, September 4 through Thursday, September 6
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, September 7
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open. 

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Tuesday, September 4 through Thursday, September 6
Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, September 7
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound
I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #43 - August 23, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will continue with relocating concrete barriers requiring temporary freeway lane closures. Please be aware that outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

In observance of the Labor Day holiday, no closures will occur the evening of August 31 through September 3.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, August 27 through Thursday, August 30
Lane closures will be required each night from 9 pm to 5 am the following morning. No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, August 27 through Thursday, August 30
Lane closures will be required each night from 10 pm to 6 am the following morning. No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound
I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #42 - August 15, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will continue with relocating concrete barriers requiring temporary freeway lane closures. Please be aware that outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details: 
Monday, August 20 through Thursday, August 23
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, August 24
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, August 20 through Thursday, August 23

Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, August 24
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project

Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound
I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project

The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #41 - August 9, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Freeway lane closures will continue to allow crews to remove concrete barriers along Interstate 215. Please be aware that outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, Monday, August 13 through Thursday, August 16
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, August 17
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, August 13 through Thursday, August 16
Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, August 17
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open. 

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound
I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at
1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #40 - July 31, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will continue with removing concrete barriers along I-215 requiring freeway lane closures.

As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Saturday, August 4 and Friday, August 10
Lane closures will be required each night from 11 pm to 7 am the following morning.
Monday, August 6 through Thursday, August 9
Lane closures will be required each night from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details: 
Monday, August 6 through Thursday, August 9
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, August 10
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.  Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #39 - July 26, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will continue with removing concrete barriers along I-215 requiring freeway lane closures. As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, July 30 - Thursday, August 2
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, August 3
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, July 30 - Thursday, August 2
Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, August 3
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details: In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details: In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.  Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #38 - July 18, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will continue with removing concrete barriers along I-215 requiring freeway lane closures. As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, July 23 - Thursday, July 26
Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, July 27
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, July 23 - Thursday, July 26
Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, July 27
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.  Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

 

WE’RE HERE TO HELP… 

For information, to ask questions and to stay connected:


Alert #37 - July 12, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will continue with removal of concrete barriers along I-215 requiring freeway lane closures. As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date, Time & Details:
Monday, July 16 - Thursday, July 19

Lane closures will be required each night from 9 pm to 5 am the following morning.
Friday, July 20
Lane closures will be required from 10 pm to 6 am the following morning.
No detours will be required during these closures since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date, Time & Details:
Monday, July 16 - Thursday, July 19

Lane closures will be required each night from 10 pm to 6 am the following morning.
Friday, July 20
Lane closures will be required from 11 pm to 7 am the following morning.
No detours will be required during these closures since at least one lane will remain open. 

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date, Time & Details:
In Effect through the End of Project

Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date, Time & Details:
In Effect through the End of Project

The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway.  Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP…

For information, to ask questions and to stay connected:

  • Call our toll-free project helpline: 1-855-44-215-INFO
  • Follow us on Twitter: www.twitter.com/RCTC
  • Visit our project website and register to receive email updates: www.i215project.info

Alert #36 - July 5, 2012

MURRIETA – The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Construction crews will remove concrete barriers along I-215 requiring freeway lane closures. As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Intermittent Lane Closures
Location: Southbound I-215 between Scott Road and Murrieta Hot Springs Road
Date and Time: Monday, July 9 through Thursday, July 12
Lane closures will be required each night from 9 pm to 5 am the following morning.No detours will be required during these closures since at least one lane will remain open.
Date and Time: Friday, July 13
Lane closures will be required from 10 pm to 6 am the following morning.No detours will be required during this closure since at least one lane will remain open.

Activity: Intermittent Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Scott Road
Date and Time: Monday, July 9 through Thursday, July 12
Lane closures will be required each night from 10 pm to 6 am the following morning. No detours will be required during these closures since at least one lane will remain open.
Date and Time: Friday, July 13
Lane closures will be required from 11 pm to 7 am the following morning. No detours will be required during this closure since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date and Time: In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed. 

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date and Time: In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph.  New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1-855-44-215-INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway. Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE'RE HERE TO HELP...
For more information, to ask questions and to stay connected:


Alert #35 — May 24, 2012

MURRIETA — The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Roadway repair work will continue along I-215 requiring freeway lane closures. As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Lane Closures
Location: Southbound I-215 between Clinton Keith Road and Murrieta Hot Springs Road
Date and Time: Tuesday, May 29 and Wednesday, May 30
Lane closures will be required each night from 9 pm to 5 am the following morning. No detours will be required during these closures since at least one lane will remain open.

Activity: Lane Closures
Location: Northbound I-215 between Murrieta Hot Springs Road and Clinton Keith Road
Date and Time: Tuesday May 29 and Wednesday, May 30
Lane closures will be required each night from 10 pm to 6 am the following morning. No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Clinton Keith Road and Scott Road
Date and Time: In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date and Time: In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph. New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1‑855‑44‑215‑INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway. Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!

WE’RE HERE TO HELP...
For information, to ask questions and to stay connected:


Alert #34 — May 17, 2012

MURRIETA — The Riverside County Transportation Commission, the California Department of Transportation and the City of Murrieta are working to widen Interstate 215 between Murrieta Hot Springs Road and Scott Road.

Roadway repair work is planned along I-215 requiring freeway lane closures. As a reminder, the outside freeway shoulders have been reduced to eight feet within the project limits and will be in place for the duration of the project.

Construction activity is planned as follows:

Activity: Lane Closures
Location: Southbound I-215 between Clinton Keith Road and Murrieta Hot Springs Road
Date and Time: Mon., May 21, Tues., May 22, Wed., May 23 and Thurs., May 24
Lane closures will be required each night from 9 pm to 5 am the following morning. No detours will be required during these closures since at least one lane will remain open.

Activity: Lane Closures
Location: Northbound I-215 between Clinton Keith Road and Murrieta Hot Springs Road
Date and Time: Mon., May 21, Tues., May 22, Wed., May 23 and Thurs., May 24
Lane closures will be required each night from 10 pm to 6 am the following morning. No detours will be required during these closures since at least one lane will remain open.

Activity: Freeway Shoulder Reduction
Location: Northbound and Southbound I-215 between Scott Road and Clinton Keith Road
Date and Time: In Effect through the End of Project
Please be advised that outside freeway shoulders are reduced in width to eight feet along the I-215 construction corridor between Murrieta Hot Springs Road and Scott Road. Motorists and emergency responders should exercise caution within these freeway shoulders and request CHP assistance as needed.

Activity: I-215 Speed Limit Reduced
Location: Northbound and Southbound I-215 between the I-15/I-215 Junction and Scott Road
Date and Time: In Effect through the End of Project
The freeway speed limit has been reduced to 55 mph. New speed limit signs have been posted. Please be aware that traffic fines increase in the construction zone.

NOTE: Information contained in this construction alert is subject to change without notice, based on weather, field conditions or other operational factors. We regret any inconvenience these changes may create. For more information about construction activity, please call and leave a message on the project information line at 1‑855‑44‑215‑INFO. Calls will be returned by the next business day.

The project will add one lane in each direction to Interstate 215, creating three northbound lanes and three southbound lanes within this six-mile section of freeway. When completed, the project will reduce traffic congestion and delays, improve connections between Riverside and San Diego Counties, enhance goods movement and decrease air pollution from cars that now sit idle on the freeway. Construction began spring of 2011 and is expected to last about 16 months. Throughout construction, remember to Slow for the Cone Zone!